: Additional percentage allowances (loading) are applied for specific regions like Hill Stations , Forest Areas, or mining zones (e.g., 5% to 25% extra depending on motorability and elevation) . Organization of Content

Lists the hourly or daily rental rates for equipment such as JCBs, mixers, cranes, and rollers.

Specific rate data from the 2018-19 documents (including those for the KUWSDB) provide insight into the level of detail within the SoR. For instance:

: Lists rates for construction equipment like excavators, rollers, and mixers, including loading and unloading charges.

: A significant administrative change was the reduction of the interest rate on capital cost from 11% to 9% .

| Item Code | Description | Unit | Rate 2018-19 (₹) | | :--- | :--- | :--- | :--- | | 101 | Earthwork excavation in ordinary soil | cum | 180.00 | | 804 | Providing and laying reinforced cement concrete (M20 grade) | cum | 5,250.00 | | 1201 | Plastering with cement mortar (1:6) – 12mm thick | sqm | 98.00 | | 2531 | Providing vitrified tiles (Flooring) | sqm | 520.00 |

For engineers, contractors, and procurement officers, accessing the 2018-19 SOR in PDF format is crucial for historical data analysis, project auditing, and understanding material cost benchmarks. What is the PWD Schedule of Rates (SOR)?

Karnataka PWD Schedule of Rates 2018-19. This document appears to be a schedule of rates for construction items in Dharwad Circle, 2018-2019 SR Bangalore | PDF - Scribd